Product Lead Time Guide
To assist our customers,
we maintain a limited supply of equipment that can be shipped according
to the following schedule. Larger quantities can be scheduled to meet
your installation requirements:

| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
C20 |
5 Days |
Gateway
C111 |
5 Days |
| Gateway
C21 |
5 Days |
Gateway
C112 |
5 Days |
| Gateway
C22 |
5 Days |
Gateway
C114 |
5 Days |
| Gateway
C110 |
5 Days |
Gateway
C3000 Series |
7 Days |

| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
C120 |
3 Days |
|
|
| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
C130 |
5 Days |
Gateway
C132 |
5 Days |
| Gateway
C131 |
5 Days |
Gateway
C134 |
5 Days |
| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
C200 |
5 Days |
Gateway
C202 |
5 Days |
| Gateway
C201 |
5 Days |
Gateway
C204 |
5 Days |
| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
C250 |
5 Days |
Gateway
C252 |
5 Days |
| Gateway
C251 |
5 Days |
Gateway
C254 |
5 Days |

| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
500 |
7 Days |
Gateway
550 |
7 Days |
| Gateway
530 |
7 Days |
|
|

| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
700 |
7 Days |
Gateway
900 |
7 Days |
| Gateway
800 |
7 Days |
|
|

| Product/Model: |
Lead
Time/ARO: |
Product/Model: |
Lead
Time/ARO: |
| Gateway
1000-A |
7 Days |
G1000
SPC |
5 Days |
| Gateway
1000-B |
7 Days |
G1000
Quad |
5 Days |
| Gateway
1000-C |
7 Days |
G1000
PQuad |
5 Days |
| Gateway
1000-D |
14 Days |
G1000
WAN |
5 Days |
| Gateway
1000-E |
14 Days |
G1000
WAN/DSU |
5 Days |
| Gateway
1000-F |
14 Days |
G1000
WAN4 |
5 Days |
| Gateway
1000-G |
14 Days |
G1000
WAN/C |
5 Days |
| G1000
E-10 |
5 Days |
G1000
WAN/P |
5 Days |
| G1000
E-100 |
5 Days |
G1000
bri |
14 Days |
| G1000
TR |
5 Days |
G1000
pri |
14 Days |
| G1000-4PC |
7 Days |
G1000-8PC |
7 Days |
| G1000-4PC/P |
7 Days |
G1000-8PC/P |
7 Days |
| G1000-MPC |
14 Days |
G1000-Mod |
14 Days |
| G1000
MPC/P |
14 Days |
Gateway
V.35-F |
3 Days |
| G1000
RAS-1 |
14 Days |
G1000
RAS-2 |
14 Days |
| G1000-FR/DTE |
2 Days |
G1000-FR/DCE |
2 Days |
| G1000-B-RK |
3 Days |
G1000-C-RK |
3 Days |
| G1000-B-PS |
14 Days |
G1000-C-PS |
14 Days |
| G1000
CPU |
7 Days |
G1000
PROC |
7 Days |
| G1000-48V |
14 Days |
G1000
VGA |
5 Days |
Delivery times are effective May 15, 2008 and are subject to change
without notice.
|